Schedule of values tab
Vendor change orders have their own schedule of values pages. You can add a schedule of values, so you can see the quantity or value the change order has against a component.
You can add new or existing Schedule items. Items added to this page are added to the Schedule of values at the contract level only after the VCO is published. When you add a value-only schedule item to a vendor change order, only the Value field is editable.
Import and export schedule items
You can use the VCO schedule of values template to quickly add schedule items and then import them to a vendor change order. Use the import template to add new schedule items or edit existing items. For more information about how to use the template, refer to the Instructions tab of the Microsoft Excel template.
For information about importing, see Imports and exports.
Delete a schedule item
When a schedule item is not needed in the contract, you can delete it via the Vendor change order Schedule of values tab. When you delete a schedule item, the item shows in the register with a strikethrough, and it cannot be edited. The Schedule quantity and Unit price values are moved to the Change order adjustment section as negative values. When you execute and publish the vendor change order, the schedule item is deleted with a strikethrough in the parent contract.